L.W.R.A.December 2010 Letter to Council
On December 12, 2010 LWRA drafted an official letter to the Limerick Township Council regarding proposed changes to the Zoning by-law. At stake is the ability to build boathouses on the shoreline, even for water-access only cottages. Changes to the proposed by-laws were passed by the departing township council at the November meeting. The LWRA wishes to address these changes before they could become a permanent part of the zoning by-law. The complete text of the letter to council is available here:
LETTER TO REEVE GOLEM AND LIMERICK TOWNSHIP COUNCIL
A brief summary of the subdivision agreement concerning Limerick
Lake lots.
The subdivision agreement between the Township of Limerick and the
developer Trident Members Inc. regulates the way in which
development will proceed on Trident’s lands. This particular
agreement contains clauses that are standard in such agreements in
Ontario, tailored to the specifics of the Ontario Municipal Board
approval and the site.
The bulk of the agreement concerns the changes which will take place
on the land. The preamble contemplates that the Township will
appoint an Municipal Engineer, and Section
48 states that Trident will reimburse the Township for all costs
incurred in retaining the Engineer. Section 10 requires that Trident
appoint the Owners Engineer who must, as stated in a schedule,
provide stamped and authorized drawings of the work to be done. The
agreement works on the premise that the township's enforcement
officer is the Municipal Engineer, assumed to be making decisions as
a professional engineer and not in a political manner.
The Municipal Engineer must approve virtually everything that
happens on site, usually in advance of the work - clearing, grading
and gravelling roads, installing culverts, and building the
community facilities - occurring.
Section 13 requires that the Municipal Engineer must approve
the drawings provided by the Owner’s Engineer before work begins.
Section 16 requires Trident
to submit a schedule of work (including the timing sequence) before
work begins. Some matters, such as an estimate of cost for Phase One
requires approval but this estimate is included in a schedule so
approval is pro-forma. Section 18 states that cost estimates for
subsequent phases, which are not in the schedule, need approval.
Section 23, requires Trident to obtain approval from the Municipal
Engineer of any contractor working on the land, although this does
not seem to apply to those involved in the construction of
buildings. Section 24 requires Trident to get approval of work
proposed in each Phase.
Before beginning work, Trident is required by Section 24 to have
written permission of the Township (not the municipal engineer)
called Authorization to Commence Works (.
Once Trident has that
authorization, it must give the Municipal Engineer at least 96 hours
notice before work actually gets underway. Works must then proceed
expeditiously (Section 25.)
As work proceeds, it will be monitored by the Municipal Engineer,
who must approve any changes to standards set out schedules to the
agreement (Sections 11 and 25.) Work not done within certain time
periods will require further approvals (Sections, 13, 14 and 15.)
When work is done improperly the Municipal Engineer shall notify
Trident (Section 28) to remedy the situation within seven days. When
work is done improperly, there are substantial remedies available in
Section 28. With the authority of the Township, the
Municipal Engineer can
remedy the situation at the cost of Trident; the Township can use
the Performance Guarantee to pay any costs incurred and it can also
refuse to issue any further permits.
Section 18 outlines the amount of the Performance Guarantee which is
equal to 100% of the cost
estimate of the work needed in any phase. For phase one, this
amount is $200,000, set out in a schedule, and
this is secured by a letter of credit. The township can draw
on this guarantee to remedy any problem (Section 19.) Section 38
allows the guarantee to be reduced by the amount of work done. The
Owner’s Engineer must prepare estimates of the cost of work in the
other phases (Section 17.)
Section 12 states that work will proceed in phases, as set out in a
schedule. Sections 8 and 9 state that work (including work on
utilities) will begin within 12 months of the agreement -
that is, by
September 21, 2011 - and be
fully completed within three years. Section 36 conflicts with
Section 12, stating Trident has two years to complete Phase One, and
four years to complete the rest of the development. Section 37
states the Municipal Engineer will determine when work in a Phase is
complete.
Section 32 states the Township has the power to the withhold
building permits if work is not done properly, and Section 34 gives
the Township the ability to withhold the Authorization to Occupy if
work is not done properly.
Section 14 requires that before building permits for houses can be
given, a professional engineer shall have certified that storm water
manager facilities, the grading and drainage plan, and the erosion
control plan, have all be completed properly.
Section 15 allows the Municipal Engineer to intervene if
these plans are not carried out.
Section 54 states Trident cannot assign this agreement without the
approval of the township. This ensures that the Township assure
itself of the bona fides and financial capability of any purchaser
of the site.
Section 69 sets out the details of approvals given by the Ontario
Municipal Board, such as the location of the recreation facility and
beach, pathways, no septics within 300 meters of the high water mark
of Limerick Lake, and the information required to be given to
purchasers. Section 2 sets out that there will be 110 serviced lots
developed in four phases.
John Sewell.
July 6, 2011.
December 2010 Letter to Council
On December 12, 2010 LWRA drafted an official letter to the Limerick Township Council regarding proposed changes to the Zoning by-law. At stake is the ability to build boathouses on the shoreline, even for water-access only cottages. Changes to the proposed by-laws were passed by the departing township council at the November meeting. The LWRA wishes to address these changes before they could become a permanent part of the zoning by-law. The complete text of the letter to council is available here:
LETTER TO REEVE GOLEM AND LIMERICK TOWNSHIP COUNCIL
The Trident Subdivision -- An Update -- Summer, 2010
As noted in the last newsletter, Trident was gradually clearing off all
the remaining conditions needed for approval of their subdivision plan.
Prior to the April 6th meeting of Township Council, Trident sent forward
the Subdivision Agreement and accompanying documents for their approval
by Council. However, in the course of the proceedings, it was discovered
that due to what we believe was a misunderstanding by the township's
lawyer and as a result, our legal representative, in fact, one of the
required documents necessary to fulfill all the conditions had not been
signed off by the township's engineering consultants, Jewell
Engineering. The document is of some importance since it is the lot
development plan showing to quote from the condition "all dwelling,
sewage and well envelopes and their respective separation distances and
shall be of sufficient detail to establish that each lot can accommodate
an individual on-site sewage disposal system (septic system) that
conforms to the requirements of the Ontario Building Code."
Since that time, through the township lawyer, Jewell Engineering has
been asking that Trident produce this lot development plan for the first
phase of the development (30 lots). In addition, Jewell Engineering has
raised some issues with post-development runoff and watercourses and has
asked Trident for more detail to ensure that there are adequate
safeguards in place. As a result of the need to produce the information
required by Jewell Engineering and the Township, Trident requested and
the Township agreed to an extension to Friday, June 11th.
As of today, May 29th, it is too soon to tell how this will play out by
June 11th. The OMB Committee of LWRA is continuing to monitor
developments and will post updates as they occur.
Shoreline Advisor Program
Want to extend the life of your septic system? Concerned about
erosion on your property? Interested in ensuring the value of your
shoreline property?
Your lake association is working in partnership with the Lakeland
Alliance to provide the services of a trained and qualified Shoreline
Advisor.
The Advisor will come to your property, review your specific concerns
and provide practical advice on how to make improvements that enhances
the enjoyment of your waterfront and benefits the health of your lake.
The Shoreline Advisor Program is:
· Free! There is
no charge to you.
· Non-Regulatory.
We do not report to any level of government.
· Voluntary. It’s
up to you to participate.
· Confidential. We
strictly follow federal privacy laws.
To find out more about the program and to sign up for your free
consultation please contact:
Michael Gibbs
Program Coordinator
Phone: (705) 745-3238 xt. 207
Email: lakelandalliance@cogeco.net
www.lakelandalliance.net